Kashkaval Cheese Production Lines

Curd Draining Drum

Curd Filtration Drum  Curd filtration drum is used to filter the whey in the curd coming from the cheese vat. It has a perforated drum with a diameter...

Machine Overview

Curd Filtration Drum 

Curd filtration drum is used to filter the whey in the curd coming from the cheese vat.
It has a perforated drum with a diameter of 1 mm. This drum rotates continuously and the curd that passes through the drum is filtered. During this process, the spiral pipe inside the drum enables the curd to move inside the drum.
Whey discharged from the drum is filtered into the tank below.
The filtered whey is sent to the curd boiling tank through the whey pump.
The capacity of the whey pump is selected by making flow pressure calculations for each enterprise.
The drum and boat are made to be easily removable and removable for easy cleaning.
The drum, whey tank, pipe connections and whey pump are made of AISI 316 quality material because they operate in an acidic environment.

What is Curd Screen Drum?  What Is Curd Drum Used For?  What are the Technical Specifications of a Curd Drum?  What are the Prices of Curd Drums?

 Curd Drum

It is used to filter the whey contained in the curd coming out of the cheese process tank.

A drum with holes of 1 mm diameter rotates continuously and the curd is passed through the drum and strained.  During this process, the spirally produced pipe inside the drum allows the curd to move through the drum.

The waters filtered from the drum drain towards the whey trough at the bottom.

The filtered whey is sent to the whey storage tank or, if it will be processed, to the curd boiling tank by means of a whey pump directly connected to the boat.

The capacity of the whey pump is selected by calculating the flow pressure for each business.

The drum and the boat are manufactured in a way that can be easily disassembled for easy cleaning.

Drum, whey tub, pipe connections, and whey pump are produced from AISI 316 quality material since they work in an acidic environment.

 Curd Drum Technical Details

  • The whey filtered from the curd is collected in the trough under the drum.
  • It filters 10 tons of curd per hour with its Ø830×1300 mm 300micron drum.
  • Optionally, a pump can be added for evacuation.
  • For any emergency response, there is one “EMERGENCY STOP” button on the panel and one next to the machine.
  • There is a 10 RPM reducer.
  • There is a CIP system inside the drum.
  • Food-grade P1000 material is used at the product outlet.
  • Made of 304 quality stainless steel.
  • Drum speed adjustment is available.

You can contact us for the price information of Curd Drum.

Items Defined During Technical Review

Product and RecipeProduct characteristics and process stages
CapacityHourly or batch production target
Line ConnectionsUpstream and downstream equipment integration
AutomationControl, recipe and operator requirements
UtilitiesWater, electricity, steam and compressed-air availability
SiteLayout, access, cleaning and maintenance clearances

Documents

Datasheets and Project Documents

The correct datasheet revision is shared after capacity, connections and options are confirmed.

Request a Datasheet

Before Quotation

Information to Prepare

  • Product name, recipe and target capacity
  • Existing equipment list and layout dimensions
  • Water, electricity, steam and compressed-air utilities
  • Automation level and required delivery time

Frequently Asked Questions

Curd Draining Drum decision notes

How is the correct capacity determined?

Capacity is engineered according to the product recipe, batch or continuous operation, operating hours, upstream and downstream equipment and the target output.

Can this machine be integrated into an existing line?

Yes. Existing equipment, connection points, available space, utilities and automation infrastructure are reviewed before the integration scope is confirmed.

Which information is required for a quotation?

Target product, required capacity, operating schedule, available utilities, site dimensions, automation expectations and any current layout or process documents are required.

Are dimensions and options standard?

The final dimensions, material grade, connection sizes, control level and optional equipment are defined for the approved project scope.

WhatsApp Get a Quote